New Commercial Construction

Below are the required documents and information that Pittsylvania County Community Development requires before issuing a building permit for new commercial construction projects. 

  • One digital (pdf) copy of sealed (architect or engineer) plans, including all electrical, mechanical, and plumbing drawings emailed to Community Development
  • One paper copy of sealed plans submitted to Community Development
  • Approved site plan
  • Completed building permit application
  • Erosion and Sediment Control Permit

Improving Existing Commercial Construction

The following documents are required for additions and upfits of existing commercial properties. 

  • One digital (pdf) of sealed (architect or engineer) plans, including all electrical, mechanical, and plumbing drawings emailed to Community Development
  • One paper copy of sealed plans submitted to Community Development
  • Completed application
  • Approved site plan (if needed)
  • Asbestos certification

Inspection Types and Sequence

The list of inspections shown are a typical construction order. If there is a question of what inspection should be done at what time, please contact the Office of Community Development.

Footings
Foundation
Temporary Electric
Plumbing Groundwork
Electrical Groundwork
Slab
Framing
Electrical Rough-In
Mechanical Rough-In
Plumbing Rough-In
Insulation
Water Line
Sewer Line
Electrical Above-Ceiling
Framing Above-Celing
Building Final